Similar Posts
Even MORE Condos on the Corner
ByDonFrom YIMBY.com:
Earlier this month, developer Ranger Properties paid $22,000,000 for two buildings at the corner of University Place and East 13th Street, in the heart of the Village near Union Square. Then EV Grieve reported that longtime stalwart University Place Gourmet had shuttered, along with a Chinese laundry around the corner on 13th Street.Now plans have been filed to construct a seven-story apartment building on the site at 34 East 13th Street, and Adjmi Architects is designing. There will be six apartments spread across 15,550 square feet of residential space, for a very spacious average unit of 2,591 square feet. They’ll definitely be condos, with just one apartment per floor. Six stories of apartments will be stacked on top of 3,200 square feet of ground floor retail
Amenities listed on the Schedule A include a “private/public” roof deck (maybe there will be both!) and a gym in the cellar.
The 3,300-square-foot property is currently home to three buildings—a four-story apartment building on the corner that has University Gourmet on the ground floor, a single-story building housing a doggy day care, and a three-story apartment building with the laundromat.
Demolition permits have not yet been filed to knock them down.
Before Ranger Properties snapped up the assemblage for $1,100 per buildable square foot, the site hadn’t changed hands since 1980.
However, 34 East 13th Street will seem small compared to the 23-story tower planned one block south at 100 University Place. Harry Macklowe is developing the building, which will stand 309 feet tall and include 52 apartments. Other projects in the hood will also be high-end condos, including 17 East 12th Street and the nearly complete garage conversion at 12 East 13th Street.
What’s Going On with the Burned-Out Building?
ByDonCurbed reports: The curvy low-rise building at 61 Fifth Avenue, devastated by fire in 2006, has been marked for death ever since the structure—a former Scrafft’s luncheonette (see photo at top left circa 1940)—was sold to a developer in early 2008. An architect was quickly enlisted to draw up plans for a 10-story building with apartments and ground-floor retail, and it was made clear that the current 61 Fifth Avenue was too far gone to be preserved in any manner. Has the economy put a pause on those plans? Perhaps, but broker-blogger Andrew Fine reports that demolition permit was issued for the property in December, so the wrecking ball could come calling any day now.
Final Gentrification of Union Square
ByDonThe northeast corner of Union Square has now been swept clean of its last small independent businesses as Tammany Hall preps for its big upgrade. One less deli, one less smoke shop. And so it goes.
Latest Construction Update: More of the Same
ByDonFrom The New School:
Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.
The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.
DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.
The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.