New School Construction Update

This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

Similar Posts

  • Good News: A New Chocolate Shop

    At long last, L.A. Burdick Chocolate is returning to the City they love!  In late October, L.A. Burdick Café (5 East 20th Street, 212 796-0143) opened featuring their award winning hot chocolate and renowned chocolate mice and bonbons.  The café is open seven days a week serving hot and cold drinks, homemade pastries and a full selection of chocolates. 

  • Italian Paradise Due at Madison Sq.

    From the NY Times:
    Eataly, a giant market for artisanal Italian food products that opened in Turin two years ago, signed a lease this morning for an even larger location at 200 Fifth Avenue. (23rd St.) With 32,000 square feet of food halls and restaurants, Eataly New York will be twice the size of the Turin original. The partners in the venture are B&B Hospitality Group, the company behind nearly 20 restaurants around the country operated by Joseph and Lidia Bastianich and Mario Batali, along with Oscar Farinetti and Luca Bassigo, the Italian founders and managing partners of Eataly. There will also be an 8,000 square foot rooftop garden, although the plans for that space are still being worked out. “I’m not sure whether it will be for beer, sausage and pizza or just beer and sausage,” Mr. Batali said in a phone interview today from a beach in Spain.

  • Latest New School Construction Update

    Next week (April 9 to April 13), Superstructure work will continue at the 12th and 13th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 16 to April 20), we will continue superstructure concrete and slabs on the 1th and 14th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be CLOSED on Saturday, April 7th.