New School Construction Update

This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

Similar Posts

  • Latest New School Update

    Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

    The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

    This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

  • Latest New School Construction Update

    Next week (February 6 to February 10), Superstructure work will continue at and 4th and 5th floor levels. The following week (February 13 to February 17), we will continue superstructure concrete and slabs on 4th, 5th and 6th floor levels.

    This weekend the site will be open on Saturday, February 4th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    14th Street Con ED vault utility connection street work will continue per DOT Permit granted for weekends only.

  • In Happier News, A New Tea Shop

    Visit Koi, at 32 Union Square East. They say:

    A celebration, a date or just a relaxing break in the day, there is always a reason to get together around a cup of KOI tea. KOI brings joy to the world. Freshly brewed tea and flavorful ingredients, prepared with passion are the key to KOI’s authentic taste and the reason why people come back again and again. In each and every KOI store, the staff is keen to share our happiness and love of tea with you. They do their best every day to make your experience memorable. Hear the sound of tea being brewed, of ice being crushed, and of laughter. Smell the aroma of our freshly prepared ingredients. Be excited by the chewiness of our milk tea pearls. Enjoy the fun and comfortable surroundings. And the warmth of our tea shakers. With KOI, happiness happens naturally.