Latest New School Construction Update

Next week (March 5 to March 9), Superstructure work will continue at 6th and 7th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (March 12 to March 16), we will continue superstructure concrete and slabs on the 7th floor level.

This weekend the site will be open on Saturday, March 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work we will be having the boilers delivered to the site on Saturday along the 5th Ave. entrance to the site. The 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.