Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.
Additionally, Con Ed will be doing street connections on 14th street.
Next week (July 23 to July 27), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will begin on 13th st. with the aid of a small crane. We have relocated the 5th ave. sidewalk shed/pedestrian walkway to the exterior of the building.
The following week (July 30 to August 3) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.
This weekend the site will be open on Saturday, July 21st for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City.
In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 10 more instances like this until we finish our superstructure in early June.
Therefore next week (April 2 to April 6), Superstructure work will continue at the 9th and 10th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (April 9 to April 13), we will continue superstructure concrete and slabs on the 10th and 11th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, March 31st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities.
Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.