Next week (November 19 to November 23), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors along 14th st. has been completed and the crane has left the job. The site will be closed on the 22nd for the holiday but will be open Friday the 23rd and Saturday the 24th.
The following week (November 26 to November 30) Material and equipment deliveries and installation work will continue on all floors.
This weekend the site will be open on Saturday, November 17th for interior related activities between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.
Next week (January 21 to January 25), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The site will be closed for the holiday on Monday, the 21st.
The following week (January 28 to February 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.
This weekend the site will be open on Saturday, January 19th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.
Watch your mail for news of the upcoming annual meeting, including proxy forms and Zoom dial in instructions.
This week (June 6-10), contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.
The following week, we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.
Concrete foundation walls will progress.
Due to an increasing number of thefts of UPS packages which are left unattended by the UPS delivery man outside shareholders’ doors, the procedure will now change. UPS will no longer leave packages unattended upstairs. Instead, he will place them behind the locked door off the lobby, to which he and Niall will have a key. A notification of package arrival will be on the bulletin board. You can then get in touch with Niall to get the package.