More Water Shutoffs Thurs. and Tues.
You’ve surely noticed the water main repairs happening along 13th St. This will lead to water shutoffs at 830AM to perhaps 3PM on Thursday the 26th and Tuesday the 31st, and perhaps other times.
Replacing City Tavern at 22 East 13th St. will be All’Onda, which appears to be a high-end Italian spot focusing on seafood. The Chef is a veteran of both Morimoto and Ai Fiori.
Next week (June 18 to June 22), Mechanical equipment and work will continue at the 17th and 18th floor levels. The superstructure concrete work will be completed on the building by the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site is scheduled for demobilization on Saturday, the 25th.
The following week (June 25 to June 29), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, June 16th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
All businesses in the Bowlmor building with the exception of the pita place have now closed. Demolition (plus two years of construction) now seems imminent.
They pretended like they would be back, but vegan-friendly Blossom du Jour on our block of 13th St. is done.
As per the Governor’s Executive Order issued April 15, everyone is required to wear face covering in the form of a mask, scarf, or other reliable protection of the nose and mouth while in public. Also, every building occupant is to wear face covering while you are within any common area of the building including hallways, stairwells, elevator, lobby, laundry room, etc.
Most shareholders/owners are signed up for online payment of maintenance/common charges. We strongly encourage those who are not already signed up to please contact your AKAM Management Executive for additional information.
Below are a few other reminders and best practices (as applicable to your building):
Please see the following COVID-19 related links you may find helpful:
CDC.gov – COVID-19 Updates and Best Practices / NYC.Gov – COVID-19 Updates and Best Practices
As the New York Pause period now extends through May 15, 2020, we have listed various types of stay-at-home things to do which may interest you:
Please join us in continuing to thank all building staff members for their continued hard-work and dedication. We would also like to thank all building volunteers, including members of the Board, for their valuable time and input.
Any day now, in the space formerly occupied by The Adore on 13th.