Zephyr Zuckerman, the lovable, hapless heroine of Daphne Uviller’s Super in the City, is back. In Hotel No Tell, she’s armed and undercover as a concierge at a Greenwich Village hotel, tracking down a missing hundred grand. Please join third-generation Villager Daphne Uviller as she reads from Hotel No Tell which will be available for purchase and signing. (More information)

Similar Posts

  • Update on Union Square Construction

    Here’s an update on Union Square reconstruction:

    Work is progressing quickly to repave the 16th Street transverse. Crews are laying a new concrete base to better support the asphalt pavers for this heavily-trafficked portion of the park. Special care is being taken to preserve the root systems of the elm trees that bisect the pathway, and access to the center lawn for the disabled will be part of the final design. Repaving is expected to be completed by Labor Day.
    The center and east play areas are also moving along, with equipment installation nearly complete for both sections. The enormous Big Mountain play feature, fabricated by a silo manufacturer on Long Island, was welded together on site last week. The bulk of the remaining work will encompass retaining wall, decorative fence and bench installation, and final landscaping. In other construction news, Pavilion roof waterproofing, flashing and cornice work continues, as does new plaster work on the interior ceiling. Concrete and paver installation on the east plaza was recently finished, and excavation will soon begin on the east sidewalk south of the 16th Street transverse.

  • Latest New School Construction Update

    Next week (February 25 to March 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. We have begun dismantling the construction hoist on the building exterior and will continue to do so for the upcoming weeks.

    The following week (March 4 to March 8), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, February 23rd for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.

  • New UPS Procedure on 14th St. Side

    Due to an increasing number of thefts of UPS packages which are left unattended by the UPS delivery man outside shareholders’ doors, the procedure will now change. UPS will no longer leave packages unattended upstairs. Instead, he will place them behind the locked door off the lobby, to which he and Niall will have a key. A notification of package arrival will be on the bulletin board. You can then get in touch with Niall to get the package.

     

    Please address any questions to Niall.

  • Latest New School Construction Update

    Next week (February 6 to February 10), Superstructure work will continue at and 4th and 5th floor levels. The following week (February 13 to February 17), we will continue superstructure concrete and slabs on 4th, 5th and 6th floor levels.

    This weekend the site will be open on Saturday, February 4th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    14th Street Con ED vault utility connection street work will continue per DOT Permit granted for weekends only.