Latest New School Construction Update

Next week (November 21 to November 25), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25 and 11/26, weather pending. The following week (November 28 to December 2), we will continue superstructure concrete and slabs. Street utility connection work will continue.

Similar Posts

  • Latest New School Construction Update

    Next week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.

    The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Union Square Partnership’s Annual Report Has Arrived

    To get a sense of the pulse of the neighborhood, check out the USP’s ANNUAL REPORT. It’s full of interesting plans and action items, such as:

    Public Space Activations: This summer, USP is rolling
    out new seating areas, enhanced landscaping, the
    second annual mural along the 14th Street Busway,
    and hosting an Oonee Pod Mini, a prototype for safe
    bike storage.

    Park Upgrades: In partnership with NYC Parks, USP
    will develop a Union Square Park infrastructure
    plan that includes upgraded utilities, irrigation, and
    bathrooms amenities, as well as a preservation plan
    of the entire district’s tree canopy.

    Since January 2021, 46 new businesses have opened in and around Union Square.

  • Union Sq. Traffic Will Be Rerouted

    Here’s the pretty big news about upcoming traffic redesign and new pedestrian areas in and around Union Square:

    A plan to reshuffle traffic around Union Square and add a new pedestrian plaza nearby has been given the final green light after months of contentious debate.

    Community Board 5 voted overwhelmingly in favor of the Department of Transportation’s plan for the square despite continuing cries from a group of vocal residents who say the changes will only make traffic in the congested neighborhood worse.

    The revised plan, which the DOT will begin implementing in the coming months, will restrict traffic to one-way westbound on E. 17th Street between Broadway and Park Avenue South.

    Broadway will be narrowed to one lane from 17th to 23rd streets, and a new pedestrian plaza will be added to the east side of Broadway between 17th and 18th streets. The exact design of the plaza, including whether or not it will have tables and chairs like Herald Square and Times Square, is still up for debate.

    To improve traffic on Park Avenue South, southbound cars will be prohibited from turning left at 18th Street, while northbound cars will be banned from turning left onto 19th and 23rd streets, among other restrictions.

    Numerous dedicated turning lanes will also be added, in addition to new protected bike lanes and revised parking schemes.

    The DOT’s Ryan Russo said the department hopes the plan will make the stretch more pedestrian-friendly, less chaotic and cut accidents in half.

    Nonetheless, a handful of residents continued to complain that they’ve been left out of the decision process and haven’t been given enough time to consider the changes.

    “I think this plan is being rushed to the extreme and rammed down neighbors’ throats,” lawyer Milton Meyers, 63, a 20-year resident of 18th Street and Irving Place, told the standing room-only crowd at the CB5 meeting Thursday.

    Artist Silvia Kolbowski, who has collected more than 300 neighborhood signatures opposing the plan, accused the DOT of caring less about improving safety than pushing through another pedestrian plaza as part of a larger city plan.

    “If the issue was safety at the crossings, then surely this plan is overblown,” said Kolbowski, 56, who has lived on East 18th Street at Park Avenue South for a decade. The plan, she said, will create “nothing but chaos.”

    While such opinions were overwhelming when the idea was first presented back in April, opposition has faded as the DOT has made revisions, including dropping an initial plan to completely shut down Broadway to traffic between E. 17th to 18th streets at certain times of the day.

    Numerous organizations, including representatives from New York University, the Union Square Green Market, the Union Square Partnership, and Transportation Alternatives have now joined in support of the plan.

    “This neighborhood has a chance to have some significant safety improvements that other neighborhoods are clamoring for,” dance instructor, Detta Ahl, 31, who lives in Morningside Heights but frequently cycles in the area, told the audience.

    The plan was ultimately adopted on a ‘pilot’ basis, with a provision that the DOT return in three and six months after implementation to report on the results.