Lastest New School Construction Update

Next week (November 14 to November 18), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A street crane will be moved into position early on Wednesday the 11/16 on 13th street to place structural steel in the building and should be out by the end of the day, weather pending.

The following week (November 21 to November 25), we will continue superstructure concrete and slabs. Street utility connection work will continue. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25.

This weekend the site will be open on Saturday, November 12th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • Latest New School Update

    Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

    The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

    This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

  • What’s Going On with the Burned-Out Building?

    Curbed reports: The curvy low-rise building at 61 Fifth Avenue, devastated by fire in 2006, has been marked for death ever since the structure—a former Scrafft’s luncheonette (see photo at top left circa 1940)—was sold to a developer in early 2008. An architect was quickly enlisted to draw up plans for a 10-story building with apartments and ground-floor retail, and it was made clear that the current 61 Fifth Avenue was too far gone to be preserved in any manner. Has the economy put a pause on those plans? Perhaps, but broker-blogger Andrew Fine reports that demolition permit was issued for the property in December, so the wrecking ball could come calling any day now.