Latest New School Construction Update

Next week (November 21 to November 25), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25 and 11/26, weather pending. The following week (November 28 to December 2), we will continue superstructure concrete and slabs. Street utility connection work will continue.