Blossom du Jour Has Wilted

They pretended like they would be back, but vegan-friendly Blossom du Jour on our block of 13th St. is done.

Similar Posts

  • Farmer’s Market Sales Way Down

    The New York Times reports:

    This season’s inclement weather affected farmers’ markets as much as their crops, and customers lost early on never really came back. Just ask Michael Hurwitz, director of greenmarkets for the Council on the Environment of New York City.

    “God, this was a tough year,” Mr. Hurwitz said. Market problems snowballed from the spring, when less produce than usual was available because of rain, cool weather and late planting on vendors’ farms. “That impacted customers coming back to market,” he said. “Spring is not for making money; it’s for getting customers in. Fall is for making money — and less people all season came to the markets.”

    Those all-important weekends, including the two biggest market weekends of the season in mid-October, were rainy, and that meant fewer shoppers, Mr. Hurwitz said. At the largest market, in Union Square, business was off by as much as 40 percent this season. The economic crisis compounded the low turnout, though on the bright side, he said, it generally kept vendors from raising prices.

    But farmers like John Glebocki had little choice. Mr. Glebocki is an Orange County farmer who sells his produce exclusively at 22 farmers’ markets, most of them in the New York City system. He figures he lost nearly 50 percent of his 80 acres of mixed vegetables, but he has faith in his customers. “People understand it’s a low production year,” he said, “and if we have to tack on another quarter a pound.”

  • Latest New School Construction Update

    Next week (January 28 to February 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

    The following week (February 4 to February 8), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, January 26th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.