Latest New School Update

Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

Similar Posts

  • No Danny Meyer in Park

    There was a rumor that leading restauranteur Danny Meyer wanted to run the new restaurant to be established in the Union Square Park pavilion. Not true, says Meyer, but he will be taking over the cursed Wakiya space in the Gramercy Park Hotel and establishing an Italian restaurant there.

  • Latest New School Construction Update

    Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.

    Additionally, Con Ed will be doing street connections on 14th street.