The Trials and Tribulations of 61 5th Avenue
Read all about the sales difficulties of 61 5th Avenue and see lots of pictures here.
Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.
Additionally, Con Ed will be doing street connections on 14th street.