Latest New School Construction Update

Next week (January 23 to January 27), Superstructure work will continue at and 3rd, 4th and 5th floor levels. All sidewalk sheds around the site have been opened up.

The following week (January 30 to February 3), we will continue superstructure concrete and slabs on 4th and 5th floor levels.

This weekend the site will be open on Saturday, January 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work this Saturday we will be installing the main auditorium trusses at the 3rd floor level. During the installation 13th St. will be closed as well as some lanes on 5th Ave. Pedestrian traffic will also be temporarily closed on the east side of 5th ave. for safety during the lifts.

Please do not hesitate to contact me with any questions or concerns. Thank you.

Jane R. Crotty
Senior Vice President
George Arzt Communications, Inc.
123 William Street, 22nd Fl.
New York, NY 10038
T (212) 608-0333

Similar Posts

  • What’s Going On with the Burned-Out Building?

    Curbed reports: The curvy low-rise building at 61 Fifth Avenue, devastated by fire in 2006, has been marked for death ever since the structure—a former Scrafft’s luncheonette (see photo at top left circa 1940)—was sold to a developer in early 2008. An architect was quickly enlisted to draw up plans for a 10-story building with apartments and ground-floor retail, and it was made clear that the current 61 Fifth Avenue was too far gone to be preserved in any manner. Has the economy put a pause on those plans? Perhaps, but broker-blogger Andrew Fine reports that demolition permit was issued for the property in December, so the wrecking ball could come calling any day now.

  • More on Union Square Park Restaurant

    A court has blocked–for now–the use of the Union Square Park pavilion as a privately run restaurant. “Opponents object to what they see as the privatization of park space and insist the city needs approval from the state legislature before moving forward. The new ruling lets the city renovate the Pavilion and rehabilitate the bathrooms, but halts plans to lease it out for a restaurant.”

    Gothamist has links to all the latest news.

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.