Latest New School Construction Update

In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 10 more instances like this until we finish our superstructure in early June.

Therefore next week (April 2 to April 6), Superstructure work will continue at the 9th and 10th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (April 9 to April 13), we will continue superstructure concrete and slabs on the 10th and 11th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, March 31st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities.

Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

Similar Posts

  • More on NYU’s Massive Plans

    From the Greenwich Village Society for Historic Preservation:

    NYU recently revealed its draft Environmental Assessment Statement and draft Scoping Document for its massive proposed zoning changes and taking of public land to allow its planned twenty-year expansion in Greenwich Village. These documents provide greater detail about what NYU is planning, what the potential impacts are of their proposed changes, and how NYU will be required to analyze those impacts for the public review process of their application.

    Community Board #2 will be holding a public hearing on the documents and the response to them on Thursday, May 5 (time and location TBD). Following the Community Board hearing, the City Planning Commission will hold a hearing before the documents are finalized and the review and analysis takes place. This process is expected to take several months. After that, the public hearing, review, and approval process for the actual proposed zoning changes and transfers of public land may take place.

  • Goodbye Garden of Eden, Hello Atherea

    Garden of Eden is gone and missed. In its place will come Atherea, a more organic, health-food focused market and cafe. Does that mean $$$$? Probably. Here’s what they say:

    “At Atherea Natural Market, we are leaders in the niche of premium organic products and your trusted resource for individuals who are dedicated to integrating health and sustainability into their lifestyles. At Atherea Natural Market, we understand that food is foundational to our well-being. Our rigorously curated selection encompasses awide array of local organic and NON-GMO fruits and vegetables, nutrient-dense pantry essentials, organic prepared foods andcatering, along with our third party tested vitamins and supplements. We partner exclusively with local NYS organic farmers who strictly adhere to biodynamic and regenerative farming standards that enhance the health of our ecosystems. This dedication ensures that our customers have access to products that are not only organic and NON-GMO but also responsibly sourced, harvested, and sold within our market.”
    Yep, sounds $$$$
  • Yet Another Construction Update from the New School

    Next week (August 15 to August 19), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 22 to August 26 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, August 13th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

  • Park Arrests Way Up

    Something has gone wrong in Union Square Park this summer. Complaints about illegal behavior, drug use, and vagrancy have led to a 320% increase in police citations. Now the police are patrolling much mor aggressively, as are hired security teams from the Union Square BID.