Latest New School Construction Update

Next week (July 2 to July 6), Mechanical equipment and work will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Wednesday, July 4th, for the holiday.

The following week (July 9 to July 13), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.

This weekend the site will be open on Saturday, June 30th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • New School Construction Update

    The latest from the New School:

    Next week (January 17-21), Urban Foundations will continue to drill solder piles on 14th Street. The pile driving rig is scheduled to arrive on site, and will begin driving piles on 5th Ave, moving South. Loading out of debris and earth from the site will continue. Hand chopping of the existing foundation wall in the South East corner of 65 Fifth will also be taking place. Installation of the fence along the USC Courtyards will take place, followed by the removal of the existing protection.

    The following week (January 23 – 28), Urban is anticipated to continue driving piles along 5th Avenue, then continuing to 13th Street moving East. Excavation of earth and installation of timber lagging between piles on 14th street is planned to begin. Loading out of debris and earth from the site will continue. Demolition of existing foundation wall in SE corner of 65 Fifth by hand chopping will continue.

  • Artist Will Go Homeless to Draw Attention to Homelessness

    A Queens man is hoping to turn sleeping on the streets into big bucks for the homeless.

    Yusef Ramelize, a 33-year-old graphic designer, will leave his Ozone Park apartment Sunday and take up residence in Union Square Park. He won’t shower and he won’t have shelter during his “Homeless for One Week” project.

    “My reasoning for doing this is to inspire people to make sacrifices within their own lives,” Ramelize said of his project, now in its second year.

    He raised $3,635 in March 2009 and donated it to the Coalition for the Homeless. This year’s beneficiary will be the Food Bank of New York.

    Ramelize will hand out flyers and keep a videotaped diary of his experiences in order to help elicit donations on his website, homelessforoneweek.com.

    “It’s really about me pushing myself to see how much of a sacrifice I’m willing to make every year to get the word out,” Ramelize said.

    Ramelize chose Union Square to pay homage to his biggest inspiration, Mohandas Gandhi, who is immortalized with a statue on the west side of the park.

    “That’s one of the reasons I did it here,” Ramelize admits. “He wanted to bring peace around him, and he was willing to sacrifice his life.”

    As if braving the elements for seven days wasn’t enough, the slender Ramelize will also be fasting from sunrise to sunset for the Muslim holy month of Ramadan.

  • Latest New School Construction Update

    Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

    The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

    This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.