Latest New School Construction Update

Next week (May 6 to May 10), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs. Additionally we will be working on the roofs of the building.

The following week (May 13 to May 17), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

This weekend the site will be open on Saturday, May 4th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

Similar Posts

  • More Broadway Pedestrianization North of Union Square

    Expanded pedestrian space and more cycling lanes are central to a planned redesign of Manhattan’s Broadway between E. 17th and E. 21st streets, city officials announced on Monday.

    The changes are subject to public outreach — but Department of Transportation officials said they could mimic a change to other areas of Broadway between Union Square and E. 50th Street, where crews in recent years have added more pedestrian plazas, outdoor dining space and wider crosswalks designed to keep pedestrians safe from crashes.

    DOT officials also said they’re considering adding a two-way bike lane between E. 17th and E. 21st streets, which already has a one-way southbound lane for cyclists.

    The city earlier this year completed an overhaul of Broadway between E. 25th and E. 32nd streets, adding more space for pedestrians, another two-way bike lane and other infrastructure designed to make motorists drive slower.

    “This next phase of Broadway Vision will provide the same kind of vibrant public spaces connecting Union Square and Flatiron, just like our administration is doing with incredible success across the entire city,” Mayor Eric Adams said in a statement.

    The latest planned improvements are just north of Union Square — and just south of where a taxi driver jumped a sidewalk last year, sending several pedestrians to the hospital.

  • A Refresher Course on the Metronome Wall Art

    from Gothamist.com

    The Metronome, the hulking piece of public art omnisciently keeping time in Union Square, has been an object of both fascination and derision for twenty years. The work is meant to be a rumination on time and rituals, and features a massive rock, a whirring digital clock that means wildly different things depending on who you ask, and a hand from Union Square’s own equestrian statue of George Washington that points to its history.

    Yet something seems to be off about the Metronome. As a tipster pointed out to Gothamist, the steam that was supposed to emerge from the center of the piece hasn’t worked in ages, it doesn’t seem to have been maintained in a while, and even its website is defunct.

    That might be because the Metronome wasn’t ever finished, as Kristin Jones, the artist who created the piece along with Andrew Ginzel, tells Gothamist. It was always meant to be more than be a “gaping hole,” “void,” or “smoldering anus,” as it’s been called before. Jones says that the “dismissive and inadequate” upkeep from The Related Companies (the real estate company that owns the property) means the Metronome has never looked, or kept time, as they intended it to.

    According to Jones, the piece, a nod to European clocks’ different mechanisms for telling time, originally was going to emit steam twice daily (at noon and midnight) along with bursts of sound. It barely has, if ever. She also notes that in spite of “periodic upgrades” to the numeral display, the clock was “never correct in the first place,” especially because the artists never saw it before it went up and it never had the flexible software it needed.

    Jones knows that people seem baffled about what the numbers represent: They don’t, say, represent the national debt or the time left until the Earth implodes, and it is indeed a clock meant to be read left to right. (The left half, at least, which displays the time since midnight. The right half, which shows the time remaining until midnight, should be read right to left.)

    Curiously, the Metronome, steam and all, is prominently displayed on Related Rentals’ website, currently hawking one-bedroom apartments at the Union Square locale for a starting price north of $5,500 monthly rent. (“Live Luxuriously in a Work of Art,” it reads.) Related did not reply to Gothamist’s request for comment.

    The Metronome came about when Related approached the Municipal Art Fund in 1995, as The New York Times reported, about what to do with the building’s wall space. Eventually Related and the Public Art Fund held a competition where artists submitted proposals for the wall. Kristin Jones and Andrew Ginzel ended up getting the commission, and in 1999 the Metronome first began ticking along at Union Square.

    Since then, the artists say, they haven’t had input, or knowledge, as to how the artwork is being maintained, if at all. Jones says she’d personally rather see the Metronome be torn down instead of continue in its current state. “Since they don’t [correspond with us] I’m not interested in seeing the light bulb in the hole where there’s no steam,” Jones says. “It doesn’t make any sense.”

    Stephen Ross, the billionaire developer and chairman of Related, is responsible for Hudson Yards’ Vessel, the wastebasket-like stairway to…somewhere that owns your photos. Ross hasn’t been shy about his distaste for the piece Related had a hand in creating at One Union Square South. “It was a disaster,” he told The New Yorker last year. “That thing where the smoke comes out? Whatever the hell it is.”

    “Union Square South was and is a machine for enrichment, as is so much of real estate development today often without sincere civic vision,” Jones and Ginzel wrote in a statement. “Witness Hudson Yards. If Mr. Ross maintains ‘The Vessel’ as he has Metronome, pity the public who must contend.”

  • Latest New School Construction Update

    Next week (November 19 to November 23), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors along 14th st. has been completed and the crane has left the job. The site will be closed on the 22nd for the holiday but will be open Friday the 23rd and Saturday the 24th.

    The following week (November 26 to November 30) Material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, November 17th for interior related activities between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.