Latest New School Construction Update

Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.

Additionally, Con Ed will be doing street connections on 14th street.

Similar Posts

  • A Replica of Anne Frank’s Hidden Annex is Coming to the Area

    The Center for Jewish Society, at 15 East 16th St., will be presenting a very special exhibit, beginning on January 27th.

     

    For the first time in history, the Anne Frank House will present a pioneering experience outside of Amsterdam to immerse visitors in a full-scale recreation of the Annex, where Anne Frank, her parents and sister, and four other Jewish inhabitants spent two years hiding to evade Nazi capture.

    Anne Frank The Exhibition gives visitors of all ages the chance to learn about Anne Frank, not as a victim but through the multifaceted lens of her life—as a girl, a writer, and a symbol of resilience and strength. More than 100 original collection items from the Anne Frank House in Amsterdam, including several never-before-exhibited artifacts, help to convey the context that shaped Anne’s life, death and posthumous fame. Her diary is one of the most translated books in the world.

    Order tickets here. 

  • Latest New School Update

    Next week (October 31 to November 4), Contractors will finish excavating and loading out material. Concrete foundation walls and slab on grade work will conclude as well as underground electrical and plumbing work. DOT approved street connections to underground utilities on Fifth Avenue will progress. Superstructure work will continue at cellar, 1st, and 2nd floor levels.

    The following week (November 7 to November 11), we will continue superstructure concrete and slabs. Street utility connection work will continue. A sidewalk shed will be erected around the perimeter of the site, subject to DOB approval, to protect pedestrians from superstructure work.

    This weekend the site will be open on Saturday, October 29 for foundation and superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, waterproofing and rebar for concrete placement and use of the crane and equipment to support all activities. We may pour a section of slab on grade concrete on Saturday. There will be no rock excavation or rock chopping.

  • Latest New School Construction Update

    Next week (July 23 to July 27), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will begin on 13th st. with the aid of a small crane. We have relocated the 5th ave. sidewalk shed/pedestrian walkway to the exterior of the building.

    The following week (July 30 to August 3) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

    This weekend the site will be open on Saturday, July 21st for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City.