  • Latest New School Construction Update

    Next week (March 12 to March 16), Superstructure work will continue at 7th and 8th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 19 to March 23), we will continue superstructure concrete and slabs on the 8th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. We also have an approved After Hours Variance for Thursday and Friday in anticipation of a large concrete pour happening on one of those days.

    This weekend the site will be open on Saturday, March 10th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition, tomorrow, Friday the 9th, we will be starting operations at 6am in anticipation of a large concrete pour and will more than likely, with notification of the Department of Buildings, be going later into the evening to finish. Also on the weekend of the 10th the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • A 14th St Resurgence

    The Union Square Partnership reports:

    Amid the broader success of the Union Square area in 2024, the performance of 14th Street between 1st and 6th Avenues stands out as exceptional. This segment alone welcomed 18 new businesses in 2024, including Q4 openings such as Adonis Barbershop, Upperz Café & Bar, Kamisama, and Harlem’s famous soul food restaurant Amy Ruth’s. These family-owned establishments enhance Union Square’s vibrant and diverse retail and food scene.

    Thanks to strong leasing activity this quarter, the storefront vacancy rate along 14th Street between 1st and 6th Avenues has dropped to 9%, with just one available ground-floor listing east of Broadway.

    According to LiveXYZ, this is below the average vacancy rate for Manhattan Business Improvement Districts (BIDs) (16%) and the vacancy rate for the Union Square Partnership BID as a whole (16%).

    Beyond retail growth, investments in residential developments and transit upgrades have modernized 14th Street’s appearance and accessibility at Union Square’s western gateway. The completion of upgrades to the F/L/M/1/2/3 subway station at 6th Avenue has made the station fully accessible, complementing new residential landmarks like FÖRENA (540 6th Avenue) and 101 West 14th Street at the intersection’s northern corners. Meanwhile, construction is underway on a 71-unit condominium at 525 6th Avenue on the southwest corner, poised to complete the transformation of this important intersection.

  • Union Square Trash Compactor Plunge Wasn’t Murder

    No foul play is suspected in the death of the woman who fell down her Union Square building’s trash chute in July, the city’s Office of the Chief Medical Examiner said on December 19. The body of Lara Prychodko, 48, was discovered by a building maintenance worker inside the trash compactor at Zeckendorf Towers on the corner of Irving Place and E. 15th Street on July 10, police said. Authorities believe the woman dropped 27-stories in the chute. Her body was discovered “crushed from multiple angles” in the compactor. It was not immediately clear if Prychodko’s death was accidental or a homicide, authorities said at the time.

  • Time for Summer Streets

    On Saturdays Aug. 3, 10, and 17th, enjoy 8 hours of car free streets on Park Avenue S, Union Sq E and 4th Ave, with countless programs and activities from 7AM to 3PM. Summer Streets provides space for healthy recreation and encourages New Yorkers to use more sustainable forms of transportation.