  • Latest New School Construction Update

    Next week (May 27 to May 31), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs and will be removing the sidewalk shed along 13th st. Additionally we will be working on the roofs of the building. The site will be closed on Monday, the 27th for the holiday.

    The following week (June 3 to June 7), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, May 25th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Update

    Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

    The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

    This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

  • Latest New School Construction Update

    Next week (January 23 to January 27), Superstructure work will continue at and 3rd, 4th and 5th floor levels. All sidewalk sheds around the site have been opened up.

    The following week (January 30 to February 3), we will continue superstructure concrete and slabs on 4th and 5th floor levels.

    This weekend the site will be open on Saturday, January 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work this Saturday we will be installing the main auditorium trusses at the 3rd floor level. During the installation 13th St. will be closed as well as some lanes on 5th Ave. Pedestrian traffic will also be temporarily closed on the east side of 5th ave. for safety during the lifts.

    Please do not hesitate to contact me with any questions or concerns. Thank you.

    Jane R. Crotty
    Senior Vice President
    George Arzt Communications, Inc.
    123 William Street, 22nd Fl.
    New York, NY 10038
    T (212) 608-0333