Sona Brings High-End Indian Food to the ‘Hood
New near Union Square, SONA reimagines the wonders of Indian fare in a space that evokes a bygone era of a boisterous yet elegant India—all within the heart of New York City. Visit at 36 East 20th St.
Next week (February 11 to February 15), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.
The following week (February 18 to February 22), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. The site will be closed on Monday, February 18th, for the holiday.
This weekend the site will be open on Saturday, February 9th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.
I write to remind all that the lower 8 floors of this building are still a construction site which is regulated by the Department of Buildings. New School has heard your complaints but at this time we do not control this site. It is our hope that when we take over the building we can make some necessary changes. The University Center is a LEED building with many energy saving designs incorporated into the building so that we will be good neighbors.
Next week (December 23rd to December 27th ), material and equipment deliveries and installation work will continue on the academic floors inside the building. (Site closed on Christmas)
The following week (December 30th to January 3rd ), material and equipment deliveries and installation work will continue on academic floors (Site closed on New Year’s Day)
This weekend the site will be open on Saturday and Sunday, December 21st and 22nd for interior activities between the work hours of 7AM and 7PM as permitted by the City.
Dominique Ansel is opening a third bakery in Manhattan. The French pastry chef, famous for inventing the cronut in 2013, has signed a 15-year lease n at 64 University Place, between East 10th and 11th streets. The new bakery is located on the ground level of that yet-to-be-completed 11-floor luxury apartment complex.
Next week (June 25 to June 29), Mechanical equipment and work will continue at the 17th and 18th floor levels. The superstructure concrete work will be completed on the building by the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (July 2 to July 6), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.
Go here to read today’s New York Times Real Estate section analysis of what’s going on in Union Square. Some interesting facts and figures, including the detail that One Union Square South is only 30 percent sold and that the white-brick Victoria (across 14th St.) recenty added “Union Square” to its name.