Latest New School Construction Update
ByDonNext week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.
The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
Latest New School Construction Update
ByDonNext week (July 2 to July 6), Mechanical equipment and work will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Wednesday, July 4th, for the holiday.
The following week (July 9 to July 13), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.
This weekend the site will be open on Saturday, June 30th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
Baohaus 2 Comes to 14th St.
ByDonThe neighborhood is more fun now that crazy chef Eddie Huang’s Baohaus 2 is open on 14th between 2nd and 3rd. A bao is a little Chinese sandwich usually stuffed with some kind of pork. The inventive and very funny Huang, who has Taiwanese roots, is making many variations on the theme, plus coming up with all kinds of other funky Chinese home cooking. Check it out.
Fresh and Co. Is No Mo’
ByDonThe corner of 4th Ave. and 13th St. is vacant once again.