Results from Latest Union Square Partnership Survey

USP received valuable feedback on streetscape elements and public space amenities around the neighborhood, including priorities for infrastructure improvements on surrounding streets and within Union Square Park.

Street trees (91%) and City Benches (87%) received the highest rates of satisfaction among City-operated elements, and seasonal plantings (95%) and bistro tables + chairs (92%) received the highest rates among USP-operated amenities. Respondents expressed a desire for additional trees and seating districtwide, as well as bike racks, protected bus shelters, and investments in the park to enhance landscaping, lighting, public restrooms, and the dog run.

The survey also revealed top priorities for public realm investments, which align with the Union Square-14th Street District Vision Plan. The transportation improvements rated with the highest level of importance include safer pedestrian crossings (97%), pedestrian streets (92%), and an ADA-accessible subway (87%). 90% of respondents would like Street Seats implemented around the district. USP is incorporating this feedback into the next phases of Vision Plan planning and design efforts.

Similar Posts

  • Thai, Thai Again?

    We’ve had Thai restaurants as downstairs neighbors before, and now a new one may be coming to replace Corkbuzz at 13 East 13th. A liquor license application has been filed by Varith, a “family-run” Thai restaurant that has a highly regarded sister operation called Valla Table in Hell’s Kitchen run by Chuck Valla, who was a private chef prior to opening this first place in 2021. Looks good.

  • Latest New School Construction Update

    Next week (September 24 to September 28), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 1 to October 5) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

    This weekend the site will be open on Saturday, September 22nd for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

  • Latest New School Construction Update

    Next week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.

    The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.