Notice of Annual Shareholders’ Meeting

The annual shareholder’s meeting will take place on Wednesday June 30th at 7PM at the Seafarers’ and Interational House at 123 East 15th St, second floor.

At the meeting, the Board of Directors will be seeking at least one new member. If you wish to become a candidate for the Board and have your name placed on the ballot, please feel free to provide a short biography of yourself via fax (212) 986-0002 or e-mail to ymartinez@akam.com. The Board will also welcome nominations at the meeting itself.

Similar Posts

  • See the Plans for the new New School

    An invitation from the New School to attend a preview of the new building on May 6:

    April 26, 2010

    To Our Neighbors, To meet the university’s evolving needs, plans for the construction of a new University Center at 65 Fifth Avenue will continue to move forward this summer. Because The New School has made it a priority to engage the entire university in the project’s development, we invite you to view the next phase of building design at a second exhibition featuring an overview of the current plan. We will also have a model of the building on display. Please join us on May 6 from 3:30 p.m. to 5:30 p.m. in the Theresa Lang Community and Student Center on the second floor of 55 W. 13th Street. This open house will include new renderings of the building design, academic and social spaces, sustainability systems, and details about the construction schedule. As in the past, attendants will be able submit comments and ask questions of many of the principals, including New School staff, architects and professionals from the design firm and construction trades. We hope to see you there.

  • Huge Free Wine Tasting at Union Sq. Wines Saturday

    Join Union Square Wines in celebrating five years at their new location. Taste nearly one hundred wines in six hours during our Anniversary Party. Our favorite purveyors from the wine biz will be on hand to pour a wide range of varietals, regions, and styles for all attendess. Guest pourers will be showcasing their wines through two shifts, 1pm to 4pm and 4pm to 7pm – when all is said and done marathon tasters will have enjoyed a little something from almost every wine region in the world! This incredible tasting event is certain to inspire selections for the upcoming summer months. In addition to a legion of wine offerings, guest spirit Fidencio Mezcal will be serving up Joven and Classico Mezcal as well as the complex agave spirit Pechuga all day! There will be something for everyone in celebrating five years at 140 Fourth!

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.