  • Latest New School Construction Update

    Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.

    This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Free Sandwich Friday!

    Brit chain Pret A Manger had moved into the former Tisserie space at 857 Broadway (at 17th Street), and now comes official word that when it opens for a test run this Friday, it will give away 3,000 free sandwiches starting at 12:15 p.m. — provided you snag one of the flyers that will be given away at the Union Square subway entrances between 8 a.m. and 9:25 a.m. that morning. Pret is calling this the “Guinea Pig Day” for what will be their U.S. flagship (the store features a fresh design and free Wi-Fi), but for better or worse, cuy won’t be served — instead, Pret is sourcing food directly from Greenmarket vendors. The location opens fully on June 22.

  • Comestics Galore

    The Real Deal reports:

    Beauty brand NYX Cosmetics signed a lease for a new store on Union Square West, a 2,800-square-foot space on the ground floor of Brause Realty’s 75,000-square-foot commercial building at 41 Union Square West, at the corner of East 17th Street. The lease was signed earlier this month. It’s where Starbucks was before it moved.

    The youth-focused chain chose a location close to New York University and nestled among a concentration of cosmetics stores ringing Union Square, including Fresh, Bluemercury and Sephora, each within a block of the new location. On the south side of Union Square, Estee Lauder’s MAC inked a lease at the Feil Organization’s 853 Broadway two years ago.

  • Goodbye Garden of Eden, Hello Atherea

    Garden of Eden is gone and missed. In its place will come Atherea, a more organic, health-food focused market and cafe. Does that mean $$$$? Probably. Here’s what they say:

    “At Atherea Natural Market, we are leaders in the niche of premium organic products and your trusted resource for individuals who are dedicated to integrating health and sustainability into their lifestyles. At Atherea Natural Market, we understand that food is foundational to our well-being. Our rigorously curated selection encompasses awide array of local organic and NON-GMO fruits and vegetables, nutrient-dense pantry essentials, organic prepared foods andcatering, along with our third party tested vitamins and supplements. We partner exclusively with local NYS organic farmers who strictly adhere to biodynamic and regenerative farming standards that enhance the health of our ecosystems. This dedication ensures that our customers have access to products that are not only organic and NON-GMO but also responsibly sourced, harvested, and sold within our market.”
    Yep, sounds $$$$
  • Latest New School Construction Update

    Next week (June 17 to June 21), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building on 13th st. as well as taking the sidewalk shed down on 13th st. Additionally we will be working on the roofs of the building.

    The following week (June 24 to June 28), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, June 15th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.