Similar Posts
Massive East Village Demolition Ahead
ByDonNote that the entire western side of 3rd Ave. between 10th and 11th Streets save for the southernmost building has been bought up and is destined to meet the wrecking ball. The Greenwich Village Society for Historic Preservation says there are significant buildings with important stories on the block, but it seems unlikely the city will step in to stop redevelopment.
Another Bit of 65 5th Ave. Gossip
ByDonWhen the New School builds its new building on the corner, one of its major uses will be to house a consolidated Parsons School of Fashion Design, which is currently scattered among many midtown buildings. That’s according to the New School student newspaper. So expect even more groovily dressed teens outside our front doors.
The Latest on Wash. Square Park
ByDonHere’s an update.
Annual Meeting: October 12
ByDonThis year’s annual shareholder meeting will take place virtually on October 12. Watch your mail and e-mail for log-in details.Union Square Holiday Market Cancelled
ByDonCOVID strikes again. No holiday market this year. You’ll have to travel up to Bryant Park to pick up your scented candles and knitted mittens.
Latest New School Construction Update
ByDonNext week (October 22 to October 26), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.
The following week (October 29 to November 2) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.
This weekend the site will be open on Saturday, October 20th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.