6th Precinct Community Meeting, June 26th

The NYPD 6th Precinct Community Council Meeting

will take place in-person Wednesday June 26th, 7:00 PM

Location: Northwell Lenox Health Greenwich Village,

30 7th Avenue at 13th Street,

Conference Center Room 643

As part of the planned 2024 enhancements to our regular monthly meeting programs, this June meeting will include a panel of guest speakers from the NYC Department of Homeless Services and integral partner agencies: Chris Gonzalez, DSS Chief Strategy Officer, Kevin Perdomo, DHS Assistant Commissioner for Street Homeless Solutions, Tamara Felix, Center for Urban Community Services (CUCS) Community Outreach Coordinator. They will address the Homeless Crisis and how they are tackling this important issue in our neighborhood and what information our Community residents and businesses should know.

Join the leadership of the 6th Precinct, your neighbors and local businesses for an update on community affairs.  Take this opportunity to listen or to voice your thoughts in an open and informative session.  We encourage you to tell/bring a neighbor and be a part of your Community’s voice.

Coffee and treats to be provided by

Marie Blancère French Café & Bakery 301/303 6th Ave., New York

Similar Posts

  • Agata and Valentina Building Slated for Demolition?

    This report from Greenwich Village Society for Historical Preservaation notes that 64 University Place, the non-descript building currently housing Agata and Valentina, may be scheduled to meet its destiny with the wrecking ball. In its place, a 12-story building.

    Village Preservation has learned that a developer has filed plans to demolish 64-66 University Place (10th/11th Street) within our proposed South of Union Square Historic District we have been fighting to get landmarked.

    No permits have yet been filed for a new building, though we understand a 12-story building is being contemplated. The zoning for the site allows a roughly 42,000 square foot building here, of residential, commercial, and community facility uses, with about 6-7,000 square feet of additional air rights purchased from neighboring 70 University Place. By comparison, neighboring 21 East 10th Street is approximately 56,000 square feet.

    Village Preservation has been campaigning for landmark designation for this area, and our research and documentation submitted to the City shows that this building, in spite of its utilitarian looks, actually has an incredibly important history worthy of recognition and protection. While we have made some progress recently advancing our landmarking proposal, the City has nevertheless resisted landmarking the full proposed district, and Councilmember Carlina Rivera, who represents this area, has not endorsed the historic district landmarking proposal.

  • Canadian Donuts Invade Union Sq.

    A news flash about the Zen Palate site on Union Sqare East, and it’s decidedly downmarket:

    “The Riese Organization just purchased 34 Union Square (between 15th and 16th), formerly home to Zen Palate and plans to install a TGI Friday’s and a bonus Tim Horton’s in the space. Its been vacant in the two years since Zen Palate vacated due to “astronomical and non-negotiable increases” in their rent, a rent that has dropped 40% in the last six months. Choice quote: “…while many chefs in the district purchase food from the popular green market there, T.G.I. Friday’s will not join them, says Mr. Riese. ‘We are not that type of restaurant…'” Indeed.

  • Comedy in Union Square

    NYLaughs presents a free comedy night in Union Square Park on Thursday, June 5, from 6 p.m to 9:15 p.m., kicking off a weekend comedy festival around the neighborhood.

    Enjoy top comedians—from TV headliners to rising stars—curated to showcase NYC’s diverse voices. Presented with The Stand and Union Square Partnership.

  • Union Sq. Partnership Celebrates Success

    Here’s an article from The Villager about the success of the Union Square Partnership:

    The Union Square Partnership held its 24th annual meeting at the W Hotel on Thursday last week celebrating the progress of the city’s first business improvement district and the beginning of the long-awaited reconstruction of Union Square Park’s north end and the square’s northern plaza.

    Danny Meyer, Partnership co-chairperson, presented the annual Community Service Award to Debbie Hulse, the Department of Parks and Recreation’s head gardener for Union Square Park for the past four years.

    Jennifer Falk, the Partnership’s executive director, celebrated the BID’s accomplishments over the past year in sanitation (removing 1,749 tons of trash last year) and business promotion, including a new Web site, a new free walking tour and the new Visitor Map & Guide, 50,000 copies of which will be distributed in the area.

    “Every year, the Partnership makes a series of targeted investments in the beautification of Union Square Park and our partners like Debbie Hulse help us achieve our goals,” Falk said. “Debbie has poured her heart into making Union Square Park one of the most beautiful destinations in New York City.”

    Manhattan Borough President Scott Stringer spoke at the June 5 meeting and called Falk “a powerhouse” for her energy in looking after the city’s number-one BID and her concern for residents in the district.

    George Kroenert, Parks Department team leader for the Union Square north-end reconstruction, outlined the scope of the project that began at the end of April and that will triple the current playground’s size, renovate the north-end pavilion and add water and electrical connections for Greenmarket farmers’ trucks.

    The Greenmarket, now occupying the square’s west side while the north end is under construction, will return to the north end in phases as sections of the plaza are completed, Kroenert said.

    The project’s hoped-for completion date is October 2009, Kroenert said.

    “But we’re going to take our time and do the right thing,” he said. “We’re at 6 percent complete and we’ve used up 8 percent of our time, and the contractor has committed to keeping the playground closed for only one summer.”

    Meanwhile, outside of the W Hotel around the north-end plaza, exuberant demonstrators, some in costume, were protesting against the proposal to install a seasonal, private restaurant in the pavilion once it’s restored. The evening before, Reverend Billy of the Church of No Shopping, real name Bill Talen, managed to get into the construction area to hang a banner that said, “Not for Sale” from the pavilion’s roof.

    A court order last month allowed construction on the plaza and the pavilion to proceed, but restrained any work that pertains to any restaurant in the pavilion pending the outcome of a lawsuit that seeks to keep private restaurant concessionaires out of the pavilion.

    One of the protesters last Thursday, Kurt Opprecht, a member of Billionaires for Bush, the satiric protest group, came into the annual meeting at the W Hotel and during the open question period referred to “the rabble-rousers outside who don’t realize that money doesn’t grow on trees.” Opprecht said later that his remark at the meeting was meant satirically, but the satire was missed.

    Carol Greitzer, a former city councilmember who has opposed the project because of the proposed restaurant concession, was inside at the W Hotel meeting.

    “This is going to be strange coming from me, but Robert Moses built 800 playgrounds in the city and he did it without the help of commercial restaurants,” Greitzer said.

    Also on June 5, City Councilmember Rosie Mendez issued a public letter about why she supports the project after have opposed it in the past. Instead of doubling the current playground area as originally proposed, the current plan triples the playground size to nearly 15,000 square feet, Mendez noted. And instead of a year-round restaurant in the pavilion, the plan was changed to a six-month, seasonal concession. Mendez also noted that Luna Park, the previous outdoor restaurant around the outside of the pavilion, occupied 6,507 square feet. The seasonal concession planned for the pavilion is 3,732 square feet, she noted.

    “At first, I only heard from those opposed to the plan,” Mendez said. “But as the plan evolved, the feedback my office received was very mixed. Some residents expressed their support for the plan, eager to quickly build the playground and refurbish the pavilion regardless of its use.”

    Moreover, while many people said they feared that 17th St. on the north side of the plaza would be expanded and take away plaza space, the row of trees planned for the north end of the plaza will be planted a few feet into the 17th St. roadbed, increasing the size of the plaza, Mendez noted.

  • Latest New School Construction Update

    Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

    The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

    This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.