  • The Latest New School Construction Update

    This week (May 23 to May 27), Contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.

    The following week (May 30 to June 3), we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.

    Concrete foundation walls will progress.

  • Cambodian Sandwiches: The New Lunch

    Be sure to check out Num Pang, the tiny new Cambodian sandwich shop on 12th St. just around the corner from University Place. The sandwiches, prices around $7.50 are fresh, spicy, and unusual, very much like Vietnamese banh mi. Crowds have overwhelmed the place in its early days, and it’s been sold out a few times. Still, very much worth a visit, even if the prices are more than double what you would pay for something similar down in Chinatown.

  • New School Construction Update

    This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

    The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

  • Update on the North End of the Park

    Here’s the official word on how the renovations are going:

    Spring weather has brought with it a flurry of activity in Union Square Park, both in the new playground and at the construction site.  Parents and kids have been taking full advantage of the warm sunny days by swinging, climbing and sliding their way out of the winter doldrums.  The Partnership’s new landscape efforts, including more than 260 ornamental shrubs and 650 perennials, will soon be underway, as well as the creation of additional seating opportunities in the center lawn, in front of the new Pavilion entrance and around the James Fountain (a/k/a Mother & Child).

    In construction news, structural work on the Pavilion columns and ceiling beams has finished at last, and the protective plywood barriers have been removed from the front of the building, exposing the beautifully restored neo-classical interior to passersby.  As the Pavilion elevator is installed and tested, interior lighting fixtures, gates and handrails round out the final touches of building restoration work.

    Park visitors can soon make use of the restroom facilities as they, too, near completion.  Last week, eco-resin panels were mounted above the granite walls to enclose the building, allowing the final plumbing fixtures to be installed.  Once complete, the Parks Department will work closely with the Department of Buildings to inspect all systems in order to open the facilities for the busy summer season.