11-Story Building to Replace Kellogg’s Cafe on East 17th

From YIMBY:

Permits have been filed for an 11-story mixed-use building at 31 East 17th Street in Union Square, Manhattan. Located between Broadway and Park Avenue South, the through lot is steps from the 14th Street-Union Square subway hub, serviced by the 4, 5, 6, L, N, Q, R, and W trains. Ken Rosenblum under the Four Roses LLC is listed as the owner behind the applications.

The proposed 168-foot-tall development will yield 39,669 square feet, with 26,023 square feet designated for commercial space and 12,240 square feet for community facility space. The concrete-based structure will also have a cellar.

David Kubik of BKSK Architects is listed as the architect of record. The architectural firm is also responsible for the glass dome addition atop the neighboring 44 Union Square.

Similar Posts

  • Latest New School Construction Update

    Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.

    Additionally, Con Ed will be doing street connections on 14th street.

  • Latest New School Construction Update

    Next week (October 21st to October 25th), material and equipment deliveries and installation work will continue on the academic floors inside the building and we anticipate paving on 5th Ave.

    The following week (October 28th to November 1st), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 19th for interior activities between the work hours of 7AM and 5PM as permitted by the City.