State of Play Hospitality group has signed a lease to open Flight Club, a technology-enabled darts gaming facility, at 31 Union Square West in Flatiron, Manhattan. This will be the group’s first venue in Manhattan, and its ninth lease for the Flight Club brand in North America. The location will be a global flagship for the brand. Flight Club will occupy a 10,700-square-foot space at 31 Union Square West, a 16-story Renaissance Revival building designed by architect Bruce Price. The building was constructed in 1902-03 as the headquarters of the Bank of Metropolis. It was designated a city landmark in 1988 and was added to the National Register of Historic Places in 2003.
The brand’s new location is scheduled to open in late 2025, joining the building’s history of housing venues like Zippers nightclub in the early 1980s, Metropolis restaurant and club in the late 1980s, and Blue Water Grill from 1996 until recently.
“We’ve been looking for the right real estate opportunity to land Flight Club in New York for over five years, and this site has the potential to be a genuine landmark for the city and the group,” said Toby Harris, CEO of State of Play Hospitality. “Both 31 Union Square as a building and the stunning split level Flight Club space are as close to the physical brief for the brand that we could wish for. I’m confident that by complementing and retaining the character of the building, we will be able to do it justice.”
Since launching the first U.S. Flight Club in Chicago in 2018, State of Play has expanded the brand to Boston, Houston, Atlanta, Las Vegas, and Denver, with new venues set to open in Washington D.C. and Philadelphia in late 2024.
Next week (July 22 to July 26), material and equipment deliveries and installation work will continue on all floors inside the building. Asphalt work on 14th st will begin this week to tie in the finished sidewalk. We will be opening the new sidewalk on 13th st. Additionally we will be working on the roofs of the building. Furniture deliveries will take place in the afternoon along 5th ave.
The following week (July 29 to August 2), material, equipment and furniture deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, July 20th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.
All businesses in the Bowlmor building with the exception of the pita place have now closed. Demolition (plus two years of construction) now seems imminent.