  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 5 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 23 to April 27), Superstructure work will continue at the 14th and 15th floor levels. Monday, April 23rd, and Thursday, April 26th, we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 30 to May 4), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, we will have an additional crane on site at 13th st. and 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.

  • Amazing Image!

    Our new neighbor Ann Roth tells us about this incredible image of the 14th St. building that she dug up:

    “I found the image on the web, where someone was selling a hand-colored print of the 14th Street facade, from a magazine that dates to 1891. So it clearly dates to that year (or earlier), not 1899, as all the real estate ads say. I ordered it, and they immediately took it off their site, so I can’t send you the link, but I copied the image first, so I’ve attached it. I must say, I wish it still had the fancy spire. The architects were D’Oench & Simon. Albert D’Oench studied in New York and Stuttgart, and then worked for Robert Morris Hunt (who designed the Metropolitan Museum’s facade) for a while. He was the NY Inspector of Buildings for five years, which seems to have mainly involved fire safety. After that, he had a successful architectural partnership with Albert (or Bernard?) Simon, and they designed and built several fire stations in New York. D’Oench later married the mayor’s daughter. Clearly a man with good connections. The plan calls it a “store building,” built it for Mrs. Mary S. Van Beuren, who was the granddaughter and heir of Henry Spingler (who I think has a building on Union Square named after him). She lived nearby, on 14th Street, just west of 5th, and seems to have been a bit of a sharp customer, to judge from some of the legal tussles I found when I searched her name on Google.”

  • Latest New School Construction Update

    Next week (July 1 to July 5), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalk around the building on 13th st. Additionally we will be working on the roofs of the building. There will be no work on July 4th holiday.

    The following week (July 8 to July 12), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.