Yet Another Construction Update from the New School

Next week (August 15 to August 19), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 22 to August 26 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, August 13th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.