To Our Neighbors, To meet the university’s evolving needs, plans for the construction of a new University Center at 65 Fifth Avenue will continue to move forward this summer. Because The New School has made it a priority to engage the entire university in the project’s development, we invite you to view the next phase of building design at a second exhibition featuring an overview of the current plan. We will also have a model of the building on display. Please join us on May 6 from 3:30 p.m. to 5:30 p.m. in the Theresa Lang Community and Student Center on the second floor of 55 W. 13th Street. This open house will include new renderings of the building design, academic and social spaces, sustainability systems, and details about the construction schedule. As in the past, attendants will be able submit comments and ask questions of many of the principals, including New School staff, architects and professionals from the design firm and construction trades. We hope to see you there.

Similar Posts

  • From Diner to Fine European Foods

    The University Diner has finally found its new identity…as a European cookie shop. The details:

    “Almost a year after the closure of the classic diner University Restaurant, an Austrian corporation will open a specialty food shop in its place later this month, the owner of the incoming business said Tuesday.

    “Gunz Fine European Food will sell cookies, snacks and other fine foods imported from across Europe, Daniel Gunz said.

    “It will be everything from Belgian chocolate to Spanish cakes to Italian olive oil,”

  • Latest New School Construction Update

    Next week (September 26 to September 30), contractors will continue to excavate earth and rock, loading out material. Line drilling will continue as well in limited areas. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will continue. Removal of the interior earth ramp will be completed. DOT approved street connections to underground utilities on Fifth Avenue will progress. The cherry picker crane on site will be removed upon installation of the Superstructure Contractors Crane which will be stationed inside the Fifth Avenue fence.

    The following week (October 3 to October 7 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections and underground electrical and plumbing. Formwork for superstructure concrete construction will proceed.

    DEP has completed the water main repair along 13th Street. As part of this work the DEP will be completing related road repairs.

    This weekend in addition to the site being open on Saturday, September 24th for foundation related activities between the work hours of 9AM and 5PM as permitted by the City, there will also be a crane installation crew assembling a crawler crane for use by the concrete superstructure contractor.

    Crane installation will involve a partial street closure on Fifth Avenue between E. 14th and E. 13th Streets, as well as a full closure of E. 13th Street between University Place and Fifth Ave. As permitted by the City this activity is to occur between the hours of 6 AM & 9 PM with Sunday, 9/25/11 as a backup date. We don’t plan on needing Sunday for the crane installation unless the weather effects us on Saturday or something else that’s unpredictable prevents the completion of assembly on Saturday. It is anticipated that this work should be completed by end of work day but it could extend until the time allowed.

  • More on Bowlmor

    The Greenwich Village Society for Historic Preservation has been doing some reconnaissance to find out what exactly developer Billy Macklowe has planned for his new condo building that will replace Village icon Bowlmor Lanes, and what they’ve found has not heartened them: “[The building] will take the form of a short base with retail uses coming out to the streetwall, and a very tall, narrow, residential tower rising above it. At approximately 308 feet in height, this will be one of the tallest, if not the tallest, buildings in the Village. Apparently Mr. Macklowe has told elected officials that the building will be limestone rather than glass or steel