Now On Display in Union Square Park

Here’s what’s on display in the park:

Miranda July is a fiction writer (No One Belongs Here More Than You), a filmmaker (Me and You and Everyone We Know), a performance artist (Things We Don’t Understand and Are Definitely Not Going to Talk About), and an occasional sculptress. It’s that latter designation that’s the focus of a new public art installation, the comparatively terse “Eleven Heavy Things,” organized by Deitch Projects, which opened late last week in New York’s Union Square Park. (The installation will remain in the park through October 3rd.) The sculptures, many of which revolve around a line of text written in July’s own hand, prod the viewer into audience interaction. “What I look like when I’m lying,” reads one, a white tablet through which the viewer can stick his head. A trio of pedestals — labeled ‘The Guilty One,’ ‘The Guiltier One,’ and ‘The Guiltiest One’ — asks participants to gauge (and flaunt) their general culpability. Three of the sculptures are wordless “headdresses,” decorative sculptures that July compares to the dialogue-free stretches of a movie: “The shapes are those parts of this piece.”

Similar Posts

  • New School Construction Update

    The latest from the New School:

    Next week (January 17-21), Urban Foundations will continue to drill solder piles on 14th Street. The pile driving rig is scheduled to arrive on site, and will begin driving piles on 5th Ave, moving South. Loading out of debris and earth from the site will continue. Hand chopping of the existing foundation wall in the South East corner of 65 Fifth will also be taking place. Installation of the fence along the USC Courtyards will take place, followed by the removal of the existing protection.

    The following week (January 23 – 28), Urban is anticipated to continue driving piles along 5th Avenue, then continuing to 13th Street moving East. Excavation of earth and installation of timber lagging between piles on 14th street is planned to begin. Loading out of debris and earth from the site will continue. Demolition of existing foundation wall in SE corner of 65 Fifth by hand chopping will continue.

  • Latest New School Construction Update

    Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.

    This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Happy Holiday Market

    We were going to announce the opening of the Union Square Holiday Market today, but it’s been open for over a week already. Christmas comes earlier every year. Our advice: go midday. At night it’s an agita-inducing mosh pit.