New School Construction Update

The latest from the New School:

Next week (January 17-21), Urban Foundations will continue to drill solder piles on 14th Street. The pile driving rig is scheduled to arrive on site, and will begin driving piles on 5th Ave, moving South. Loading out of debris and earth from the site will continue. Hand chopping of the existing foundation wall in the South East corner of 65 Fifth will also be taking place. Installation of the fence along the USC Courtyards will take place, followed by the removal of the existing protection.

The following week (January 23 – 28), Urban is anticipated to continue driving piles along 5th Avenue, then continuing to 13th Street moving East. Excavation of earth and installation of timber lagging between piles on 14th street is planned to begin. Loading out of debris and earth from the site will continue. Demolition of existing foundation wall in SE corner of 65 Fifth by hand chopping will continue.

Similar Posts

  • Park Renovation Continues Apace

    In Union Square Park, the 16th Street transverse and eastern plaza are now open to pedestrians, complete with additional park benches along the north sides of the transverse. New asphalt pavers and crushed bluestone allow the stately elm trees along the transverse to thrive while removing the previous trip hazard, and the entrance to the center lawn is now accessible to wheelchairs. The park’s new and expanded 15,000-square-foot play space is nearing completion with Parks Department final site inspections scheduled in the next few weeks. Soon, area kids will have endless hours of fun in this creative, colorful and beautifully landscaped play space designed by Michael Van Valkenburgh Associates. The North End Project is 91% complete and the remainder of the project, including new restroom facilities and the Pavilion, are expected to be finished by the end of the year.

  • Latest New School Construction Update

    Next week (July 9 to July 13), Mechanical equipment and work will continue at the 17th and 18th floor levels. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (July 16 to July 20), we will be working on the machine room levels on the 17th and 18th floors. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, July 7th for superstructure activities as well as the demobilization of the crane from the site. In order to facilitate this effort we will be closing 13th street for the day to pedestrian and automotive traffic. Site work will begin at 6AM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.