14th St. in 1939, Part II

dd

Similar Posts

  • See the Plans for the new New School

    An invitation from the New School to attend a preview of the new building on May 6:

    April 26, 2010

    To Our Neighbors, To meet the university’s evolving needs, plans for the construction of a new University Center at 65 Fifth Avenue will continue to move forward this summer. Because The New School has made it a priority to engage the entire university in the project’s development, we invite you to view the next phase of building design at a second exhibition featuring an overview of the current plan. We will also have a model of the building on display. Please join us on May 6 from 3:30 p.m. to 5:30 p.m. in the Theresa Lang Community and Student Center on the second floor of 55 W. 13th Street. This open house will include new renderings of the building design, academic and social spaces, sustainability systems, and details about the construction schedule. As in the past, attendants will be able submit comments and ask questions of many of the principals, including New School staff, architects and professionals from the design firm and construction trades. We hope to see you there.

  • Gotham Bar & Grill Shutters After 36 Years

    Gotham Bar & Grill, the longest-running high-end dining establishment in the neighborhood, is done.

    According to Eater.com…

    After 36 years — and one major, recent chef change — fine dining trailblazer Gotham Bar & Grill is closing. Saturday, March 14 will be its last night of service, according to an email sent to customers.

    Restaurants across the city are closing temporarily as new measures to curb the coronavirus outbreak have led to declines in sales, but Gotham will not be reopening.

    The closure follows a brief tenure from its new chef Victoria Blamey, who started leading the kitchen only last year — and was a significant change for the longtime regulars of the storied American fine dining restaurant. The previous chef, Alfred Portale, ran the kitchen for more than three decades and through its many accolades, including Michelin stars and James Beard Awards. He left to open his first solo restaurant, Portale, in Chelsea.

    Blamey did not come into an easy situation. Much of the staff and the clientele were intensely loyal to Portale, who created dishes that became icons, like a riff on tuna tartare. He’d also been there for most of the restaurant’s tenure. Gotham opened in Greenwich Village in 1984, and he took over the large, white tablecloth establishment a year later.

    Moreover, Gotham is a fine dining legend; its menu shaped what American fine dining looks like in New York. The pressure was on for Blamey, who was expected to bring a younger crowd to the restaurant. And under her, Gotham retained its three stars in the New York Times, with Pete Wells delighting in her additions to the menu.

  • Farmer’s Market Winter Warriors

     

    An update from the Farmer’s Market:

    The time has come to flex your Winter Warrior muscles! Each year, from January through March, Greenmarkets across the city participate in the Winter Warrior Challenge. If you shop at the market during the coldest months of the year, you can win a prize (and Winter Warrior bragging rights!)!

    It’s simple to participate and fun for the whole family! All you need to do is stop by any Greenmarket Market Info Tent to pick up your Winter Warrior card. Then, every time you shop at the Greenmarket between January and March, visit the Info Tent to get your card stamped.

    Shop ten times before March 31st and win a small Greenmarket prize plus an entry into our raffle for one of our grand prizes. For details, grand prize announcements, and more, follow us at @unsqgreenmarket on Instagram!

  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June.

    Therefore, next week (April 30 to May 4), Superstructure work will continue at the 15th and 16th floor levels. Tuesday, May 1st and Friday, May 4th we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 7 to May 11), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be closed.

  • Latest New School Construction Update

    Next week (March 12 to March 16), Superstructure work will continue at 7th and 8th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 19 to March 23), we will continue superstructure concrete and slabs on the 8th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. We also have an approved After Hours Variance for Thursday and Friday in anticipation of a large concrete pour happening on one of those days.

    This weekend the site will be open on Saturday, March 10th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition, tomorrow, Friday the 9th, we will be starting operations at 6am in anticipation of a large concrete pour and will more than likely, with notification of the Department of Buildings, be going later into the evening to finish. Also on the weekend of the 10th the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.