Latest New School Construction Update

In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 10 more instances like this until we finish our superstructure in early June.

Therefore next week (April 2 to April 6), Superstructure work will continue at the 9th and 10th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (April 9 to April 13), we will continue superstructure concrete and slabs on the 10th and 11th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, March 31st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities.

Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

Similar Posts

  • Latest New School Construction Update

    Next week (May 20 to May 24), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs and will be removing the sidewalk shed along 13th st. Additionally we will be working on the roofs of the building.

    The following week (May 27 to May 31), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, May 18th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (May 13 to May 17), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs. Additionally we will be working on the roofs of the building.

    The following week (May 20 to May 24), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, May 11th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Options for the Virgin Space

    What might be next in the Virgin Megastore space? The New York Post has these rumors:

    RELATED Cos. is negotiating with several tenants at One Union Square South for the Virgin Megastore space, sources said. The chain, which was purchased by Related and Vornado Realty Trust in 2007, is closing the store in late May or early June. All US-based Virgin Megastores are due to shut down by the summer.

    Related controls the Union Square outlet, while Vornado handles the one in Times Square, which is closing in April to make way for Forever 21, the retailer that signed a megadeal for 100,000 square feet. The two real-estate giants licensed the then 11-unit Virgin chain precisely so they’d be able to control the retail in their buildings.

    Sources said the asking rent in Union Square has recently dropped to $15 million per year from $25 million. According to its CoStar Group flyers, Winick Realty is seeking $700 a foot for the 26,000-foot ground floor and $150 a foot for the 31,035-foot lower level. One Union Square South, at 52 E. 14th St., includes the hulking Metronome artwork on the lower north side of the luxury apartment tower that rises from the retail base. Some of the prospective tenants include CVS and Best Buy, which has its eye on the Circuit City space now being controlled by the bankruptcy court.

    Last fall, Related signed a letter of intent with Nordstrom Rack for about 40,000 feet. But Nordstrom in the end was reportedly loath to bring its off-price success story into the Big Apple before it snagged an A-plus site for the upscale department store flagship and nixed the Union Square opening. A Nordstrom spokeswoman said, “We will keep looking for a great spot to serve our customers.”

    There is also talk that Forever 21 might jump from Vornado’s Whole Foods building at 40-48 E. 14th St., which also hosts Filene’s Basement, and expand into 19,200 feet at One Union Square. The Forever 21 store, which opened right after 9/11, has seven years left on its deal. But a buyout doesn’t make sense in the current economic climate.