Latest New School Construction Update

Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.

This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • Union Square Cafe Nears the End

    From the Times:
    The countdown has begun to the closing of the 16th Street space that this influential restaurant has occupied for 30 years. The cafe, which was the first piece of Danny Meyer’s culinary empire, has been a favorite of New York’s publishing world and jump-started the renaissance of the Union Square area. But it will not renew its lease at a higher rent, and in the spring will relocate to nearby 235 Park Avenue South, at East 19th Street.

    To mark the final days at its current spot, from Dec. 1 to 12, the last day of service, the restaurant will switch to a three-course dinner menu called the 12 Nights of Union Square Cafe, highlighting some of its best-known seasonal dishes, including garganelli with white truffles, beef tartare, lamb braciole and Berkshire rack of pork. There are optional wine pairings from some of the restaurant’s favorite producers. Lunches will feature the regular à la carte menu:

    Dinner reservations Dec. 1 to 12 by phone only, $85 prepaid; lunch reservations up to 28 days ahead, opentable.com;

    Union Square Cafe, 21 East 16th Street, 212-243-4020,

    unionsquarecafe.com.

  • Art!

    Last Friday, NYC Parks & Recreation, CYNTHIA-REEVES PROJECTS, and the Union Square Partnership officially cut the ribbon on LOTUS, the newest piece of temporary art in the Union Square Park Triangle. LOTUS was the creation of Seoul-based artist Jaehyo Lee. To create the piece, the artist meticulously carved, shaped, burned the individual wood elements attached to a steel armature that stretches 12 feet high. The artwork has certainly made an impression as passersby who can be seen at all times of day stopping to look and touch the new art in the triangle.

    img_6796

  • Latest New School Construction Update

    Next week (November 19 to November 23), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors along 14th st. has been completed and the crane has left the job. The site will be closed on the 22nd for the holiday but will be open Friday the 23rd and Saturday the 24th.

    The following week (November 26 to November 30) Material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, November 17th for interior related activities between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.

  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June. Friday, May 4 we will have a pour at the 16th floor with a 6am start time and similar end dime, weather permitting.

    Therefore, next week (May 7 to May 11), Superstructure work will continue at the 17th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 14 to May 18), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, May 5th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work on the job site, we will have an additional crane on site at 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.