Many people believe that Union Square got its name from the many labor demonstrations that took place here back in the day. Not true. The reason for the name is much more simple: Union Square was the location of the “union” of Broadway, 4th Avenue (aka Park Ave. South), and University Place. Nothing more complicated than that.

Similar Posts

  • Latest New School Construction Update

    Next week (May 28 to June 1), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building by the end of the month. We will begin pouring concrete at 6am on Friday the 25th in order to finish in a timely manner. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.

    The following week (June 4 to June 8), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

  • Latest New School Construction Update

    Next week (September 24 to September 28), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 1 to October 5) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

    This weekend the site will be open on Saturday, September 22nd for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.