  • Latest New School Construction Update

    Next week (January 30 to February 3), Superstructure work will continue at and 3rd, 4th and 5th floor levels.

    The following week (February 6 to February 10), we will continue superstructure concrete and slabs on 4th and 5th floor levels.

    This weekend the site will be open on Saturday, January 28th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work this Saturday we will be disassembling the small crane and removing it from the site. During the demobilization 13th St. will be closed as well as some lanes on 5th Ave. Pedestrian traffic will also be temporarily closed on the east side of 5th ave. for safety.

    Please do not hesitate to contact me if you have any concerns or questions. Thank you

    Jane R. Crotty
    Senior Vice President
    George Arzt Communications, Inc.
    123 William Street, 22nd Fl.
    New York, NY 10038
    T (212) 608-0333

  • Latest Construction Update: More of the Same

    From The New School:

    Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.

    The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.

    DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

    The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.