Similar Posts
Shgcking! Dean & Deluca Shuttered
ByDonWhat a surprise that Dean & Deluca on University has closed after more than 15 years. What will become of that prime location?
Latest New School Construction Update
ByDonNext week (August 20 to August 24), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will continue on 13th st. with the aid of a small crane. The crane will remain on 13th st. for the purpose of curtain wall installation.
The following week (August 27 to August 31) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Work on 13th st should be complete by the end of this week and will be moved to 5th ave. to continue wrapping the building.
This weekend the site will be open on Saturday, August 25th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. The crane on 13th st. will not be used during the weekend. Con Ed is on site working on the building but is not in any of the streets.
Additionally over the holiday weekend the site will be open on Saturday, September 1st but will be closed on Monday, the 3rd.
More Casualties on University Place
ByDonBoth Saigon Market and Mint Kitchen are over. Two large spaces. What will replace them?




