Next week (October 29 to November 2), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.
The following week (November 5 to November 9) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.
This weekend the site will be open on Saturday, October 27th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.
Go here to read today’s New York Times Real Estate section analysis of what’s going on in Union Square. Some interesting facts and figures, including the detail that One Union Square South is only 30 percent sold and that the white-brick Victoria (across 14th St.) recenty added “Union Square” to its name.
After all the posts here about the imminent 14th St. Busway project, it died, perhaps because residents made such a fuss.