Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.
The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.
This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
A huge change of course for the proposed L train shutdown. Even though traffic on the northernmost block of University Place has been reversed, and even though the 13th St. bike lane is in full effect–and constantly blocked by trucks, of course–it now appears that none of this may have been necessary, and the upcoming 14th St. busway may not be implemented at all. Very very confusing. The MTA is ridiculous.
More changes are afoot for 14th St. in the coming years. Find out about the potential plans here.
The New York Times reports on the new busway and the potentially positive effect it has on real estate prices, although it seems certain not everyone would agree.
This week (February 4 to February 8), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.