Next week (July 1 to July 5), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalk around the building on 13th st. Additionally we will be working on the roofs of the building. There will be no work on July 4th holiday.
The following week (July 8 to July 12), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
Next week (May 6 to May 10), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs. Additionally we will be working on the roofs of the building.
The following week (May 13 to May 17), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, May 4th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.
Here is a tour of several landmark cast-iron buildings in the neighborhood, including two on our block.
Oct. 29 is the date for the park’s signature fall celebration to raise vital funds for the district’s cherished Union Square Park. Highlighting the district’s best restaurants and the vibrant Greenmarket, enjoy tastings from renowned local chefs paired with classic and innovative drinks.
Next week (October 10 to October 14), contractors will continue to excavate earth and load out material. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Underground electrical and plumbing work will continue. DOT approved street connections to underground utilities on Fifth Avenue will progress. Formwork and rebar for superstructure will continue at cellar levels.
The following week (October 17 to October 21 ), we will continue superstructure concrete and slabs, street utility connections and underground electrical and plumbing.