New School Construction Update
ByDonThis week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.
The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.
It’s Official: From Coffee Shop to Chase Bank
ByDonCoffee Shop, and its neon signage, are gone. Here comes Chase Bank.
For the Kids: A Playground
ByDonThe new and huge Union Square Park Playground looks like this.
New School Construction Update
ByDonNext week (April 11 to April 15), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin both adjacent buildings with DOB approval of our means and methods. Drilling of tie-backs, lagging and sheeting around the perimeter will progress as well. The following week (April 18 to April 23), we will continue rock excavation and loading out, as well as underpinning both adjacent buildings, lagging and sheeting.