    Next week (October 7 to October 11), material and equipment deliveries and installation work will continue on the academic floors inside the building. Additionally we will be using a lift on the sidewalk to wash the exterior of the building.

    The following week (October 14 to October 18), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 5th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • Girl Scout Cookies for Sale

    The Girl Scout troop serving girls in the city’s homeless shelters that captivated New Yorkers last year will be selling cookies again in Union Square this week.

    Troop 6000 will hold its cookie sale at Kellogg’s NYC Cafe, where members had their successful inaugural sale last year. Long lines quickly formed as news spread about the troop, and the girls ended up selling 36,000 boxes.
    This year, the troop has a goal of selling 60,000 boxes. The girls will be at the store from 1 to 6 p.m. on April 22 to April 26.

    The troop started at a homeless shelter in Queens in 2017, but grew to include hundreds of girls at 15 shelters across the five boroughs, the city announced last year. The troop is led by women and mothers also living in homeless shelters and holds meetings every week at the participating shelters.

  • Latest New School Construction Update

    Next week (April 1 to April 5), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. We will be work on the new sidewalks around the building as well.

    The following week (April 8 to April 12), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. By then end of this week we plan to have the rest of the sidewalk on 14th street complete. Additionally we plan to begin removing the sidewalk shed along 5th ave.

    This weekend the site will be open on Saturday, March 30th for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.