New School Construction Update

Next week (April 11 to April 15), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin both adjacent buildings with DOB approval of our means and methods. Drilling of tie-backs, lagging and sheeting around the perimeter will progress as well. The following week (April 18 to April 23), we will continue rock excavation and loading out, as well as underpinning both adjacent buildings, lagging and sheeting.

Similar Posts

  • Farmer’s Market Sales Way Down

    The New York Times reports:

    This season’s inclement weather affected farmers’ markets as much as their crops, and customers lost early on never really came back. Just ask Michael Hurwitz, director of greenmarkets for the Council on the Environment of New York City.

    “God, this was a tough year,” Mr. Hurwitz said. Market problems snowballed from the spring, when less produce than usual was available because of rain, cool weather and late planting on vendors’ farms. “That impacted customers coming back to market,” he said. “Spring is not for making money; it’s for getting customers in. Fall is for making money — and less people all season came to the markets.”

    Those all-important weekends, including the two biggest market weekends of the season in mid-October, were rainy, and that meant fewer shoppers, Mr. Hurwitz said. At the largest market, in Union Square, business was off by as much as 40 percent this season. The economic crisis compounded the low turnout, though on the bright side, he said, it generally kept vendors from raising prices.

    But farmers like John Glebocki had little choice. Mr. Glebocki is an Orange County farmer who sells his produce exclusively at 22 farmers’ markets, most of them in the New York City system. He figures he lost nearly 50 percent of his 80 acres of mixed vegetables, but he has faith in his customers. “People understand it’s a low production year,” he said, “and if we have to tack on another quarter a pound.”

  • Latest New School Construction Update

    Next week (October 1 to October 5), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 8 to October 12) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.

    This weekend the site will be open on Saturday, September 29th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working in the street at 14th Street and 5 Avenue.

  • Latest New School Construction Update

    Next week (July 22 to July 26), material and equipment deliveries and installation work will continue on all floors inside the building. Asphalt work on 14th st will begin this week to tie in the finished sidewalk. We will be opening the new sidewalk on 13th st. Additionally we will be working on the roofs of the building. Furniture deliveries will take place in the afternoon along 5th ave.

    The following week (July 29 to August 2), material, equipment and furniture deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, July 20th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.