The Latest New School Construction Update

This week (May 23 to May 27), Contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.

The following week (May 30 to June 3), we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.

Concrete foundation walls will progress.

Similar Posts

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • Park Arrests Way Up

    Something has gone wrong in Union Square Park this summer. Complaints about illegal behavior, drug use, and vagrancy have led to a 320% increase in police citations. Now the police are patrolling much mor aggressively, as are hired security teams from the Union Square BID.

  • Latest New School Construction Update

    Next week (July 2 to July 6), Mechanical equipment and work will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Wednesday, July 4th, for the holiday.

    The following week (July 9 to July 13), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.

    This weekend the site will be open on Saturday, June 30th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Park Renovation Continues Apace

    In Union Square Park, the 16th Street transverse and eastern plaza are now open to pedestrians, complete with additional park benches along the north sides of the transverse. New asphalt pavers and crushed bluestone allow the stately elm trees along the transverse to thrive while removing the previous trip hazard, and the entrance to the center lawn is now accessible to wheelchairs. The park’s new and expanded 15,000-square-foot play space is nearing completion with Parks Department final site inspections scheduled in the next few weeks. Soon, area kids will have endless hours of fun in this creative, colorful and beautifully landscaped play space designed by Michael Van Valkenburgh Associates. The North End Project is 91% complete and the remainder of the project, including new restroom facilities and the Pavilion, are expected to be finished by the end of the year.