Join Union Square Wines in celebrating five years at their new location. Taste nearly one hundred wines in six hours during our Anniversary Party. Our favorite purveyors from the wine biz will be on hand to pour a wide range of varietals, regions, and styles for all attendess. Guest pourers will be showcasing their wines through two shifts, 1pm to 4pm and 4pm to 7pm – when all is said and done marathon tasters will have enjoyed a little something from almost every wine region in the world! This incredible tasting event is certain to inspire selections for the upcoming summer months. In addition to a legion of wine offerings, guest spirit Fidencio Mezcal will be serving up Joven and Classico Mezcal as well as the complex agave spirit Pechuga all day! There will be something for everyone in celebrating five years at 140 Fourth!

Similar Posts

  • Latest New School Update

    Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

    The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

    This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

  • Latest New School Construction Update

    Next week (January 30 to February 3), Superstructure work will continue at and 3rd, 4th and 5th floor levels.

    The following week (February 6 to February 10), we will continue superstructure concrete and slabs on 4th and 5th floor levels.

    This weekend the site will be open on Saturday, January 28th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work this Saturday we will be disassembling the small crane and removing it from the site. During the demobilization 13th St. will be closed as well as some lanes on 5th Ave. Pedestrian traffic will also be temporarily closed on the east side of 5th ave. for safety.

    Please do not hesitate to contact me if you have any concerns or questions. Thank you