New School Construction: More of the Same

This week (June 6-10), contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.

The following week, we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.

Concrete foundation walls will progress.

Similar Posts

  • Mysterious Clock Now Counts Down to Our Doom

    In honor of Climate Week, a coalition of scientists and activists reset the digital clock with red numbers seen on the side of a building in Union Square and changed it into a “ClimateClock.” The numbers now count down the years, days, hours, minutes and seconds the Earth has left to take action to stop global warming from going over 1.5°C more than the pre-industrial levels.

    According to the organization, who aims to put the countdown clock in cities across the world, the clock’s calculation is based on the world’s current rates of emissions and the amount of CO2 that can still be released into the atmosphere. The clock simply counts down to when the “carbon budget” runs out. If the world manages to lower its emissions, more time will be left on the clock.

    The clock is based on the carbon clock made by the Mercator Research Institute on Global Commons and Climate Change (MCC) which uses data from the recent IPCC Special Report on Global Warming of 1.5°C, ClimateClock says.

    The artists responsible for putting up the clock in Manhattan told the New York Times in an interview that the display will be up until the end of Climate Week, Sept. 27. Artists Gan Golan and Andrew Boyd also told the paper that they created a mobile Climate Clock for Swedish climate activist Greta Thunberg last year before her appearance at the UN Climate Action Summit.

    With the backdrop of recent wildfires and hurricanes, which scientists say show how climate change is magnifying the extremes in weather, protests for climate action are expected all over the world on Friday.

  • Lastest New School Construction Update

    Next week (November 14 to November 18), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A street crane will be moved into position early on Wednesday the 11/16 on 13th street to place structural steel in the building and should be out by the end of the day, weather pending.

    The following week (November 21 to November 25), we will continue superstructure concrete and slabs. Street utility connection work will continue. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25.

    This weekend the site will be open on Saturday, November 12th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • The Latest Construction Update

    The New School says:

    Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.

    The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).

    DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

  • Canadian Donuts Invade Union Sq.

    A news flash about the Zen Palate site on Union Sqare East, and it’s decidedly downmarket:

    “The Riese Organization just purchased 34 Union Square (between 15th and 16th), formerly home to Zen Palate and plans to install a TGI Friday’s and a bonus Tim Horton’s in the space. Its been vacant in the two years since Zen Palate vacated due to “astronomical and non-negotiable increases” in their rent, a rent that has dropped 40% in the last six months. Choice quote: “…while many chefs in the district purchase food from the popular green market there, T.G.I. Friday’s will not join them, says Mr. Riese. ‘We are not that type of restaurant…'” Indeed.